Comparative study of construction methodologies for marine bored cast in-situ piled jetty structures (Softcopy is also available)
Dave, Disha Jay (PCM22103)
Comparative study of construction methodologies for marine bored cast in-situ piled jetty structures (Softcopy is also available) - 2024 - xx,108p.
Table Of Contents
Abstract I
Undertaking Iii
Certificate V
Acknowledgements Vii
Abbreviations Ix
Table Of Contents Xi
List Of Figures Xv
Chapter-1: Introduction 1
1.1 Background Study 1
1.1.1 Existing Marine Jetty Structures On Indian Shoreline 1
1.2 Need For Study 3
1.3 Aim 3
1.4 Objectives 4
Chapter-2: Literature Review 5
2.1 Research Papers 5
2.1.1 Construction Of Bored Cast-In-Situ Piles Using Rotary Drilling Procedure—A Case Study 5
2.1.2 Study On Construction Schedule Optimization Of Bored Pile Based On Genetic Algorithm 6
2.1.3 Cost Modeling Of A Cast-In-Situ Piles In North Eastern Part Of Tamil Nadu: A Case Study At A Selected Pile Construction Site 7
2.1.4 Comparative Analysis Method Of Work, Time, And Cost Of Concrete Spun Pile Work With Bored Pile On Construction Of The Light Rail Transit (Lrt) 7
2.1.5 Cost Forecasting Analysis On Bored And Cast-In-Situ Piles In Sri Lanka: Case Study At Selected Pile Construction Sites In Colombo Metropolis Area ...... 8
2.1.6 An Overview Of Bored Cast In-Situ Concrete Piling Work In Practice .. 8
2.1.7 Time-Cost Trade-Off Analysis On Jetty Construction Project (Case Study: Indonesian Navy Jetty Construction Project) 9
2.1.8 Socketing Of Bored Piles In Rock 10
2.1.9 Estimating Geotechnical Capacity Of Bored Cast-In-Situ Piles From Penetration Resistance 10
2.1.10 Construction Of Passenger Jetty At Mandwa Using End-On Method .. 11
2.2 Books 11
2.2.1 Foundation Design Manual 11
2.2.2 Pile Design And Construction Rules Of Thumbs 12
2.2.3 Pile Design And Construction Practice 12
2.2.4 Soil Mechanics And Foundation Engineering 12
2.3 Interview Transcript 13
Chapter-3: Research Methodology 15
3.1 Introduction 15
3.1.1 Identifying Construction Methodologies Of Marine Piling 16
3.1.2 Formulation Of Hypothesis 16
3.1.3 Data Analysis 16
3.1.4 Results And Findings 16
3.2 Bored Cast In-Situ Pile Considerations 17
3.3 End On Piling Method 19
3.4 Jack-Up Platform Method 20
Chapter-4: Components Of Jetty Structures 21
4.1 Sub Structure 21
4.1.1 Bored Cast In-Situ Concrete Pile 21
4.2 Super Structure 22
4.2.1 Precast Pile Muff 22
4.2.2 Precast Beams 22
4.2.3 Precast Planks 24
4.2.4 Cast In-Situ Concrete 25
Chapter-5: Construction Methodologies For Marine Jetty Construction 27
5.1 End On Piling Method 27
5.1.1 Construction Of Sub Structure 28
5.1.2 Construction Of Super Structure 32
5.2 Jack Up Platform Method 32
5.2.1 Construction Of Sub Structure 33
5.3 Equipment And Machineries Used 35
5.3.1 Hydraulic Piling Rig 35
5.3.2 Tremie Pipes And Hopper 36
5.3.3 Mobile Cranes 37
5.3.4 Jack Up Platform 38
5.3.5 Floating Barges 39
5.3.6 Gantry Crane 40
5.3.7 Launcher 41
Chapter-6: Hypothesis Formulation 43
6.1 Hypothetical Case Description 43
6.1.1 Approach Structure 44
6.1.2 Jetty Structure 46
6.2 End On Piling Method 48
6.2.1 Sequential Activities: Approach Construction 49
6.2.2 Sequential Activities: Jetty Construction 55
6.2.3 Time Schedule 59
6.3 Jack-Up Platform Method 62
6.3.1 Sequential Activities: Approach & Jetty Construction 62
6.3.2 Time Schedule 67
Chapter-7: Data Analysis 71
7.1 Time Comparison 71
7.2 Cost Comparison 72
7.2.1 Material & Labour Cost 72
7.2.2 Equipment And Machinery Cost 78
7.2.3 Cost Analysis 80
7.2.4 Time Vs Cost Analysis 80
Chapter-8: Results And Findings 83
8.1 Comparative Analysis Review 83
8.2 Implications For Stakeholders 84
8.3 Conclusion 84
Chapter-9: Future Scope Of Research 87
9.1 Integration Of Hybrid Construction Methodologies 87
9.2 Beyond Cost And Time: A Multifaceted Evaluation Framework 87
9.3 Integrating Risk Assessment 88
9.4 Conclusion 88
References 89
Appendix 91
CEM TH-0454 / DAV
Comparative study of construction methodologies for marine bored cast in-situ piled jetty structures (Softcopy is also available) - 2024 - xx,108p.
Table Of Contents
Abstract I
Undertaking Iii
Certificate V
Acknowledgements Vii
Abbreviations Ix
Table Of Contents Xi
List Of Figures Xv
Chapter-1: Introduction 1
1.1 Background Study 1
1.1.1 Existing Marine Jetty Structures On Indian Shoreline 1
1.2 Need For Study 3
1.3 Aim 3
1.4 Objectives 4
Chapter-2: Literature Review 5
2.1 Research Papers 5
2.1.1 Construction Of Bored Cast-In-Situ Piles Using Rotary Drilling Procedure—A Case Study 5
2.1.2 Study On Construction Schedule Optimization Of Bored Pile Based On Genetic Algorithm 6
2.1.3 Cost Modeling Of A Cast-In-Situ Piles In North Eastern Part Of Tamil Nadu: A Case Study At A Selected Pile Construction Site 7
2.1.4 Comparative Analysis Method Of Work, Time, And Cost Of Concrete Spun Pile Work With Bored Pile On Construction Of The Light Rail Transit (Lrt) 7
2.1.5 Cost Forecasting Analysis On Bored And Cast-In-Situ Piles In Sri Lanka: Case Study At Selected Pile Construction Sites In Colombo Metropolis Area ...... 8
2.1.6 An Overview Of Bored Cast In-Situ Concrete Piling Work In Practice .. 8
2.1.7 Time-Cost Trade-Off Analysis On Jetty Construction Project (Case Study: Indonesian Navy Jetty Construction Project) 9
2.1.8 Socketing Of Bored Piles In Rock 10
2.1.9 Estimating Geotechnical Capacity Of Bored Cast-In-Situ Piles From Penetration Resistance 10
2.1.10 Construction Of Passenger Jetty At Mandwa Using End-On Method .. 11
2.2 Books 11
2.2.1 Foundation Design Manual 11
2.2.2 Pile Design And Construction Rules Of Thumbs 12
2.2.3 Pile Design And Construction Practice 12
2.2.4 Soil Mechanics And Foundation Engineering 12
2.3 Interview Transcript 13
Chapter-3: Research Methodology 15
3.1 Introduction 15
3.1.1 Identifying Construction Methodologies Of Marine Piling 16
3.1.2 Formulation Of Hypothesis 16
3.1.3 Data Analysis 16
3.1.4 Results And Findings 16
3.2 Bored Cast In-Situ Pile Considerations 17
3.3 End On Piling Method 19
3.4 Jack-Up Platform Method 20
Chapter-4: Components Of Jetty Structures 21
4.1 Sub Structure 21
4.1.1 Bored Cast In-Situ Concrete Pile 21
4.2 Super Structure 22
4.2.1 Precast Pile Muff 22
4.2.2 Precast Beams 22
4.2.3 Precast Planks 24
4.2.4 Cast In-Situ Concrete 25
Chapter-5: Construction Methodologies For Marine Jetty Construction 27
5.1 End On Piling Method 27
5.1.1 Construction Of Sub Structure 28
5.1.2 Construction Of Super Structure 32
5.2 Jack Up Platform Method 32
5.2.1 Construction Of Sub Structure 33
5.3 Equipment And Machineries Used 35
5.3.1 Hydraulic Piling Rig 35
5.3.2 Tremie Pipes And Hopper 36
5.3.3 Mobile Cranes 37
5.3.4 Jack Up Platform 38
5.3.5 Floating Barges 39
5.3.6 Gantry Crane 40
5.3.7 Launcher 41
Chapter-6: Hypothesis Formulation 43
6.1 Hypothetical Case Description 43
6.1.1 Approach Structure 44
6.1.2 Jetty Structure 46
6.2 End On Piling Method 48
6.2.1 Sequential Activities: Approach Construction 49
6.2.2 Sequential Activities: Jetty Construction 55
6.2.3 Time Schedule 59
6.3 Jack-Up Platform Method 62
6.3.1 Sequential Activities: Approach & Jetty Construction 62
6.3.2 Time Schedule 67
Chapter-7: Data Analysis 71
7.1 Time Comparison 71
7.2 Cost Comparison 72
7.2.1 Material & Labour Cost 72
7.2.2 Equipment And Machinery Cost 78
7.2.3 Cost Analysis 80
7.2.4 Time Vs Cost Analysis 80
Chapter-8: Results And Findings 83
8.1 Comparative Analysis Review 83
8.2 Implications For Stakeholders 84
8.3 Conclusion 84
Chapter-9: Future Scope Of Research 87
9.1 Integration Of Hybrid Construction Methodologies 87
9.2 Beyond Cost And Time: A Multifaceted Evaluation Framework 87
9.3 Integrating Risk Assessment 88
9.4 Conclusion 88
References 89
Appendix 91
CEM TH-0454 / DAV