Role of project coordination in construction project (Mahatma Mandir convention centre : phase - 1A/1B (Also available on CD)
Rebello, Aakanksha V. (UC4613)
Role of project coordination in construction project (Mahatma Mandir convention centre : phase - 1A/1B (Also available on CD) - 2018 - vi,75,viiip.,CD-ROM
CONTENTS
Chapter 1: Introduction 1
1.1 Background 1
1.2 Need 1
1.3 Objectives 1
1.4 Scope 1
1.5 Research Method 1
1.5.1 Literature Review 2
1.5.2 Data Collection 2
1.5.3 Data Analysis 2
1.6 Research Methodology 3
1.7 Research Schedule 3
1.8 Limitation 3
Chapter 2: Literature Review 4
2.1 Introduction To Project Coordination 4
2.2 What Is Project Coordination? 4
2.3 Difference Between Project Manager And Project Coordinator 4
2.4 Functions Of Project Coordinator 5
2.5 Indian Scenario 5
2.6 Project Coordination Methods 5
2.7 Proejct Coordination Goals 6
2.8 Project Coordination Objectives 8
2.9 Key Barriers In Project Coordination 8
Chapter 3: Data Collection And Observations 9
3.1 Project Introduction 9
3.2 Project Location 9
3.3 Project Layout 10
3.4 1A/1B Phase Layout 10
3.5 Project Details 11
3.6 Resources Deployed 11
3.7 Time Line Of Phase 1A/1B 12
3.7.1 Phase 1A 12
3.7.2 Phase 1B 12
3.8 Area Statement 12
3.9 Project Matrix 13
3.10 Issue 1: Bid Process Management 20
3.10.1 EPC Contractor Bid Process 20
3.10.2 Prebid Clarifications 20
3.10.3 EPC Contractor Qualification Criteria 22
3.10.4 PMC Contract Data For Phase 1A 26
3.10.5 PMC Tender Evaluation 27
3.10.6 PMC Qualification Process 27
3.11 Changes In Design 31
3.12 BOQ Approval 37
3.12.1 BOQ Overview 37
3.12.2 BOQ Methodology 37
3.12.3 ₹ 135 Crores 37
3.12.4 ₹ 193 Crores 38
3.12.5 ₹233 Crores 40
3.13 Issue 4: Billing 41
3.13.1 RA Breakup 41
3.13.2 Attachments In Billings 41
3.13.3 RA Example 42
3.13.4 Differences In RA Submitted 42
3.13.5 Price Escalation 44
3.14 Issue 5: Extension-1B 48
Chapter 4: Data Analysis 50
4.1 Issue 1 Analysis: Bid Process Management 50
4.1.1 EPC Contractor Analysis 50
4.2 PMC Analysis 53
4.2.1 Selection Method Observations 53
4.3 PMC Tender Clause Comparison 53
4.4 Issue 3 Analysis: Approvals 54
4.5 Issue 4 Analysis: Billing 57
4.6 Issue 5 Analysis- Extension Of Work 57
4.7 Opinion Survey 59
4.7.1 Respondents 59
4.7.2 Qualitative Interview 59
4.7.3 Quantitative Interview 60
4.7.4 Similarity Variance Analysis 63
Chapter 5: Conclusion 71
Chapter 6: Recommendations 74
6.1 Future Scope Of Study 74
Bibliography 75
B TH-0758 / REB
Role of project coordination in construction project (Mahatma Mandir convention centre : phase - 1A/1B (Also available on CD) - 2018 - vi,75,viiip.,CD-ROM
CONTENTS
Chapter 1: Introduction 1
1.1 Background 1
1.2 Need 1
1.3 Objectives 1
1.4 Scope 1
1.5 Research Method 1
1.5.1 Literature Review 2
1.5.2 Data Collection 2
1.5.3 Data Analysis 2
1.6 Research Methodology 3
1.7 Research Schedule 3
1.8 Limitation 3
Chapter 2: Literature Review 4
2.1 Introduction To Project Coordination 4
2.2 What Is Project Coordination? 4
2.3 Difference Between Project Manager And Project Coordinator 4
2.4 Functions Of Project Coordinator 5
2.5 Indian Scenario 5
2.6 Project Coordination Methods 5
2.7 Proejct Coordination Goals 6
2.8 Project Coordination Objectives 8
2.9 Key Barriers In Project Coordination 8
Chapter 3: Data Collection And Observations 9
3.1 Project Introduction 9
3.2 Project Location 9
3.3 Project Layout 10
3.4 1A/1B Phase Layout 10
3.5 Project Details 11
3.6 Resources Deployed 11
3.7 Time Line Of Phase 1A/1B 12
3.7.1 Phase 1A 12
3.7.2 Phase 1B 12
3.8 Area Statement 12
3.9 Project Matrix 13
3.10 Issue 1: Bid Process Management 20
3.10.1 EPC Contractor Bid Process 20
3.10.2 Prebid Clarifications 20
3.10.3 EPC Contractor Qualification Criteria 22
3.10.4 PMC Contract Data For Phase 1A 26
3.10.5 PMC Tender Evaluation 27
3.10.6 PMC Qualification Process 27
3.11 Changes In Design 31
3.12 BOQ Approval 37
3.12.1 BOQ Overview 37
3.12.2 BOQ Methodology 37
3.12.3 ₹ 135 Crores 37
3.12.4 ₹ 193 Crores 38
3.12.5 ₹233 Crores 40
3.13 Issue 4: Billing 41
3.13.1 RA Breakup 41
3.13.2 Attachments In Billings 41
3.13.3 RA Example 42
3.13.4 Differences In RA Submitted 42
3.13.5 Price Escalation 44
3.14 Issue 5: Extension-1B 48
Chapter 4: Data Analysis 50
4.1 Issue 1 Analysis: Bid Process Management 50
4.1.1 EPC Contractor Analysis 50
4.2 PMC Analysis 53
4.2.1 Selection Method Observations 53
4.3 PMC Tender Clause Comparison 53
4.4 Issue 3 Analysis: Approvals 54
4.5 Issue 4 Analysis: Billing 57
4.6 Issue 5 Analysis- Extension Of Work 57
4.7 Opinion Survey 59
4.7.1 Respondents 59
4.7.2 Qualitative Interview 59
4.7.3 Quantitative Interview 60
4.7.4 Similarity Variance Analysis 63
Chapter 5: Conclusion 71
Chapter 6: Recommendations 74
6.1 Future Scope Of Study 74
Bibliography 75
B TH-0758 / REB